July 2, 2013 – Project Update
Work recently completed and what is coming up in the next 3 weeks
Home | Project Activities | Page 8
Work recently completed and what is coming up in the next 3 weeks
June 20, 2013 project update including recently completed work and a three look week ahead.
The Muddy River Flood Risk Management & Environmental Restoration Phase 1 Construction Project is located in the footprint generally between the Riverway downstream to Avenue Louis Pasteur.
Heavy equipment will be moved from the Intake area of the Muddy River across the Riverway thru the island across the Riverway Connector and into the old Sears Parking lot – Two lane shut downs on Riverway Connector, Riverway, Park Drive
The construction areas have been enclosed with fence and barrier to prevent access to active work areas by the public.
Project banners showing schematic representations of the existing condition and phase 1 work are being installed along the construction fence near the Louis Pasteur sidewalk, the Jug Handle sidewalk, the Brookline Ave sidewalk and the Riverway sidewalk.
Monthly MMOC meetings are held by video conference. Members of the public are welcome to attend.
Upcoming meetings:
Wednesday, March 13, 2024
Wednesday, April 17, 2024
Wednesday, May 8, 2024
Please email info@muddyrivermmoc.org
The Muddy River Restoration Project is a model of environmental stewardship. Help ensure the ongoing maintenance and resilience of the River and its parks by attending meetings, staying updated, and, most of all, enjoying our treasured urban waterway.
68 Harvard Street
Brookline, MA 02447