Thank you for attending the 2023 Muddy River Annual Meeting!
Among the many highlights of the’s MMOC 2023 Annual Meeting: Public Oversight Reimagined at Museum of Fine Arts, Boston was a comprehensive report on the
Home | Project Activities

Among the many highlights of the’s MMOC 2023 Annual Meeting: Public Oversight Reimagined at Museum of Fine Arts, Boston was a comprehensive report on the

By Matt Eddy, MMOC Staff Technicians with Bryant Associates are at Justine Mee Liff Park this week preparing to perform bathymetry measurements — assessments of

By Matt Eddy, MMOC Staff Temporary fencing has been installed throughout the 3.5 miles of the Muddy River Restoration Project. New trees, shrubs, and stone-dust

With the completion of the historic Muddy River Restoration Project in sight, we are grateful for the community advocates and friends groups who came together

With the horizon line in sight for the completion of the monumental Muddy River Restoration Project, we note the five-year anniversary of the Project’s Build

October 8, 2021. Upland trees and shrubs have been delivered and planting is underway in some areas where dredging has been completed—in the Riverway on either side of Netherlands Road and in the Fenway between Avenue Louis Pasteur and the Museum of Fine Arts (Work Areas 3, 4, 7, 8, and 9).
The U.S. Army Corps of Engineers overview focuses on preparations for the dredging work which is anticipated to begin in October 2020.
On Saturday, we implemented a traffic change in order to continue work on the project. This shift will allow us to construct the new left turn roadway from Riverway onto Park Drive North

The weather last several weeks hasn’t been as dry since the last update; however, we have continued to make progress on the project between rain storms.