Work recently completed and what is coming up in the next 3 weeks:
- The granite curbs for the Landmark Center have been installed.
- Approximately 95% of the loam for the Landmark Center has been installed.
- The existing exit sign at Landmark Center has been relocated.
- The sidewalks at Landmark Center were scheduled to be placed last Thursday and Friday.
- Soil testing was completed for Sears Parking Lot area last week.
- The signal posts have been installed at the Landmark Center.
- Cuts have been made in the roadway across the Riverway for the traffic signal conduit.
- The traffic conduit and foundations in the southside of Riverway will be completed this week.
- The mast arms for the Riverway will be installed this week.
- The new Landmark exit roadway will be opened 8 July.
- The old Landmark Exit will be removed starting 9 July.
- The sidewalk for 1A1 around the SPL will be installed the week of 8 July.
- The traffic conduit in the Riverway corridor will be completed this week.
- The traffic conduit and foundations in the Riverway island will be completed this week.
- Traffic conduits at Brookline Ave & Riverway, at Riverway and Park
- Drive and Brookline Ave an Park Drive will be installed the week of 15 July.