Phase 1 Construction Activities: 90-day Look-head for June, 2015
The weather since the last update has truly cooperated for us and helped the progress along for the project.
Home | Project Activities | Page 2

The weather since the last update has truly cooperated for us and helped the progress along for the project.
Wednesday, June 10th, 2015 8PM-6:30AM
Brookline Avenue between Park Drive and the Riverway Connector and the Riverway Connector at Brookline Avenue.
Tuesday, Wednesday, and Thursday, May 26th, 27th, 28th, 2015 8:00 PM – 6:30 AM
Brookline Avenue between Park Drive and the Riverway Connector and the Riverway Connector at Brookline Avenue.

The Muddy River Flood Risk Management & Environmental Restoration Phase 1 Construction Project is located in the footprint generally between the Riverway downstream to Avenue Louis Pasteur.

On Saturday, April 25 and 26, another traffic shift to change both vehicular and pedestrian traffic will occur to continue construction of the arch culvert underneath Riverway and to begin construction of a new left turn onto Park Drive from Riverway.

The Jug Handle roadway will be closed to vehicular and pedestrian traffic March 21-22, in order to install piping beneath the roadway as part of the Muddy River Flood Risk Management project, Boston, Massachusetts. Vehicular traffic will be detoured to Avenue Louis Pasteur for those who want to be traveling on Park Drive. (Photo by U.S. Army Corps of Engineers)

The Muddy River Flood Risk Management & Environmental Restoration Phase 1 Construction Project is located in the footprint generally between the Riverway downstream to Avenue Louis Pasteur.

The Muddy River Flood Risk Management & Environmental Restoration Phase 1 Construction Project is located in the footprint generally between the Riverway downstream to Avenue Louis Pasteur.
Excavator will be moved from the Old Sears Parking Lot onto Park Drive and continue to the Riverway work zone.