2011 - Chapter 91 Waterways License to dredge 700 feet (Phase 1) of the Muddy River
Download
Date: 7/18/11
Authors: Mass Department of Environmental Protection (DEP)
2011 - Site Plans
Download
Date: 7/18/11
Authors: Mass Department of Environmental Protection (DEP)
2011 - Cross Sections
Download
Date: 7/18/11
Authors: Mass Department of Environmental Protection (DEP)
2011 - Elevations
Download
Date: 7/18/11
Authors: Mass Department of Environmental Protection (DEP)
2011 - Project Partnership Agreement between the Department of the Army EEA, DCR, Boston and Brookline for Construction of the Muddy River Flood Risk Management and Environmental Restoration Project
Download
Date: 2/17/11
Authors: U. S. Army Corps of Engineers, EEA, DCR, Boston and Brookline
2009 - Memorandum of Understanding between the EOEEA, EOAF, Boston and Brookline, defining funding obligations and establishing a long-term Maintenance and Management Program
Download
Date: 8/5/09
Authors: EOEEA, EOAF, City of Boston and Town of Brookline
2008 - Annual Update (as required by Secretary’s certificate)
Download
Date: 4/8/08
Authors: City of Boston, Town of Brookline
2007 - Memorandum of Agreement between the Sponsors, the Emerald Necklace Conservancy, and MMOC which defines the roles and responsibilities related to maintenance and management
Download
Date: 6/7/07
Authors: Department of Conservation and Recreation, City of Boston, Town of Brookline, Emerald Necklace Conservancy, and MMOC
2005 - Certificate of the Secretary of Environmental Affairs on the SFEIRAmong other things approves the performance-based Maintenance and Management Plan included in the SFEIR
Download
Date: 4/1/05
Authors: EOEA, Secretary Ellen Roy Herzfelder
2005 - Supplemental Final Environmental Impact Report (SFEIR) submitted to MEPA.
Download
Includes Maintenance and Management Plan – The Muddy River Parks of the Emerald Necklace for the Muddy River Restoration Project
Date: 2/23/05
Authors: City of Boston, Town of Brookline
2004 - Muddy River Parks Management and Maintenance Plan.
Download
The purpose of this Management and Maintenance Plan is to provide a blueprint for the stewardship of the Muddy River parks managed by Boston, Brookline and the DCR, balancing historic landscape preservation, cultural programming and both active and passive recreation
Date: October, 2004
Authors: City of Boston, Town of Brookline
2003 - Certificate of the Secretary of Environmental Affairs on the FEIR
Download
Date: May, 2003
Authors: EOEA, Secretary Ellen Roy Herzfelder
2003 - Final Environmental Impact Report (FEIR) submitted to MEPA
Download
Date: February, 2003
Authors: City of Boston, Town of Brookline
2002 - Phase One Waiver, Final Record of Decision
Date: July, 2002
Authors: EOEA, Secretary Bob Durand
2002 - Certificate of the Secretary of Environmental Affairs on the Draft Environmental Impact Report
Download
Date: April, 2002
Authors: EOEA, Secretary Bob Durand
2002 - Phase One Waiver, Draft Record of Decision. Permitting the work in Charlesgate to proceed
Date: April, 2002
Authors: EOEA, Secretary Bob Durand
2002 - Permits: Phase 1 Muddy River Flood Control, Water Quality and Habitat Enhancement, and Historic Preservation Project
Date: October, 2002
Authors: City of Boston, Town of Brookline
2001 - The Emerald Necklace Parks Master Plan: Back Bay Fens, The Riverway, Olmsted Park, Jamaica Pond
Download
Date: April, 2001
Authors: Mass DCR, Prepared by Walmsey, Pressley Joint Venture (1989); Pressley Associates (2001)
2001 - Draft Environmental Impact Report: Phase 1 Muddy River Flood Control, Water Quality and Habitat Enhancement, and Historic Preservation Project.
Date: December, 2001
Authors: City of Boston, Town of Brookline, Prepared by Camp Dresser & McKee in association with Jason M. Cortell & Associates, Pressley Associates, Vanasse Hangen Brustlin
1999 - Memorandum of Understanding
Download
Memorandum of Understanding between City of Boston, Town of Brookline, Executive Office of Environmental Affairs (EOEA), Department of Environmental Management (DEM now part of DCR), Massachusetts Emergency Management Agency (MEMA), Boston Water and Sewer Commission (BWSC) regarding funding and administering of the Project. Proponents commit to long term maintenance of project area pursuant to a maintenance and management plan to be approved by the Secretary of Environmental Affairs.
Date: November, 1999
Authors:
1999 - Memorandum of Understanding
Download
Memorandum of Agreement between the City of Boston and the Town of Brookline relating to project: Boston Parks and Recreation Department (BRPD) to act as lead agency in management & implementation of project
Date: June, 1999
Authors: Parties to the Agreement
1999 - Certificate of the Secretary of Environmental Affairs on the ENF Requires an EIR and that EIR includes a maintenance and management plan
Download
Memorandum of Agreement between the City of Boston and the Town of Brookline relating to project: Boston Parks and Recreation Department (BRPD) to act as lead agency in management & implementation of project
Date: April, 1999
Authors: EOEA, Secretary Bob Durand
1999 - Certificate of the Secretary of Environmental Affairs Establishing a Special Review Procedure
Download
Date: April, 1999
Authors: EOEA, Secretary Bob Durand
1999 - Environmental Notification Form
Download
Environmental Notification Form (ENF) for the Emerald Necklace Environmental Improvement Master Plan and Phase 1 Muddy River Flood Control, Water Quality, Habitat Enhancement and Historic Preservation Project submitted for MEPA review EOEA File No. 11865
Date: Early, 1999
Proponents: City of Boston Parks and Recreation Department, and Town of Brookline Department of Public Works (Parks & Recreation Division)