Restoration Project Update: 90-day Look-ahead for November, 2022
The US Army Corps of Engineers, New England has issued an overview of the Restoration Project status. Their late fall update: “Hope everyone enjoyed some
Home | Long-term maintenance and monitoring

The US Army Corps of Engineers, New England has issued an overview of the Restoration Project status. Their late fall update: “Hope everyone enjoyed some

Download PDF General: The Muddy River Flood Damage Reduction Phase 2 Construction Project is located in the footprint generally between Leverett Pond to Boylston Street

With Phase 2 of the Muddy River Restoration Project set to begin in early July, the MMOC recently hosted a virtual pre-construction tour. The presenters

Dredging and landscaping were completed last fall in many of the work areas along the Muddy River. The tall, 8-foot construction fencing is being removed

October 8, 2021. Upland trees and shrubs have been delivered and planting is underway in some areas where dredging has been completed—in the Riverway on either side of Netherlands Road and in the Fenway between Avenue Louis Pasteur and the Museum of Fine Arts (Work Areas 3, 4, 7, 8, and 9).

Sep. 22, 2021. Wetland and riverbank planting and lawn seeding is beginning in some construction areas where dredging has been completed—in the Riverway on either side of Netherlands Road and in the Fenway between Avenue Louis Pasteur and the Museum of Fine Arts (Work Areas 3, 4, 7, 8, and 9)