Restoration Project Update: 90-day Look-ahead for November, 2022
The US Army Corps of Engineers, New England has issued an overview of the Restoration Project status. Their late fall update: “Hope everyone enjoyed some
Home | Plantings

The US Army Corps of Engineers, New England has issued an overview of the Restoration Project status. Their late fall update: “Hope everyone enjoyed some

Landscaping update! In late October and early November, Boston Parks and Recreation Department and its subcontractor Leahy Landscaping, Inc. installed new shrubs in the space

The return of consistently warm weather marks the beginning of the Muddy River Restoration Project’s planting season. Landscaping plans vary by work area, but in

October 8, 2021. Upland trees and shrubs have been delivered and planting is underway in some areas where dredging has been completed—in the Riverway on either side of Netherlands Road and in the Fenway between Avenue Louis Pasteur and the Museum of Fine Arts (Work Areas 3, 4, 7, 8, and 9).

Sep. 22, 2021. Wetland and riverbank planting and lawn seeding is beginning in some construction areas where dredging has been completed—in the Riverway on either side of Netherlands Road and in the Fenway between Avenue Louis Pasteur and the Museum of Fine Arts (Work Areas 3, 4, 7, 8, and 9)
On Saturday, we implemented a traffic change in order to continue work on the project. This shift will allow us to construct the new left turn roadway from Riverway onto Park Drive North