What's Happening Now

Brookline Announces the Schedule for the Willow Pond and Leverett Pond Restoration Project

The Brookline Department of Public Works has begun a vital project aimed at “restoring a living landscape in Olmsted Park, part of the historic Emerald Necklace.” The dredging work at Willow Pond and Leverett Pond will expand the water capacity and enhance the health of the pond habitats. The dual project is expected to be completed in the summer of 2027.

Brookline DPW Schedule

Week of 11/9 – Site preparation.

Week of 11/16 –  In-pond work will commence including water control and deployment of small barge for hydraulic dredging. Once water control is established and Geotube dewatering bags are in place, hydraulic dredging will commence towards the end of this week.

Weeks of 11/23 – 12/31 – Hydraulic dredging operations. This work may wrap up the week prior.

Winter 2026 – Sediment dewatering and testing.  

Late Winter / Early Spring 2027 – Sediment transport off-site. (This is dependent on temps. Frozen sediment cannot be easily moved.)

Mid to late Spring 2027 – Site restoration, invasive species management around Willow Pond and buffer zone plantings around Leverett Pond. 

Image: BrooklineDPW

Search