Home / Photos (Page 2)
Photos
-
Phase 2 preparations continue: August 2020 90-Day Look-Ahead
The U.S. Army Corps of Engineers overview focuses on preparations for the dredging work which is anticipated to begin in October 2020.
continue reading → -
Phase 2 Begins: June 2020 90-Day Look-Ahead
The U.S. Army Corps of Engineers has issued an overview of the activities that will signal the start of Phase 2 Construction. Work will begin on June 15th.
continue reading → -
US Army Corps Report – Phase 1 Construction Activities Next 90 Days – June 2016
Since the May update, the project site is looking very different.
continue reading → -
US Army Corps Report – Phase 1 Construction Activities Next 90 Days – May 2016
A lot has happened since the last update in March. The existing Riverway Intake Structure has been removed and the new Riverway Culvert Wing Wall is its place.
continue reading → -
-
US Army Corps Report – Phase 1 Construction Activities Next 90 Days – March 2016
Since the last update, we have begun excavating and shaping the Flood Risk Management (FRM) channel at the upstream limits of our Phase I project at the Riverway.
continue reading → -
US Army Corps Report – Phase 1 Construction Activities Next 90 Days – December 2015
The major project components involve the installation of a 10-foot by 24-foot box culvert under the Riverway roadway, the installation of 10-foot by 24-foot box culvert under the Brookline Avenue roadway, daylighting of the area between the Riverway and Brookline Avenue, and daylighting of the area between Brookline Avenue and Avenue Louis Pasteur.
continue reading → -
US Army Corps Report – Phase 1 Construction Activities Next 90 Days – October 2015
On Saturday, we implemented a traffic change in order to continue work on the project. This shift will allow us to construct the new left turn roadway from Riverway onto Park Drive North
continue reading → -
-
US Army Corps Report – Phase 1 Construction Activities Next 90 Days – September 2015
Continued progress since the last update at the new Riverway culvert area is the waterproofing and backfilling of the culvert; and forming and placing of the southeast concrete wingwall.
continue reading →