Planting begins in some areas: 90-day look-ahead
Sep. 22, 2021. Wetland and riverbank planting and lawn seeding is beginning in some construction areas where dredging has been completed—in the Riverway on either side of Netherlands Road and in the Fenway between Avenue Louis Pasteur and the Museum of Fine Arts (Work Areas 3, 4, 7, 8, and 9)
continue reading → -
Dredging in Leverett Pond at Olmsted Park: April 90-Day Look-Ahead
April 22, 2021. The U.S. Army Corps of Engineers has advised that dredging in Leverett Pond at Olmsted Park, Brookline (Work Area 1) will begin by the end of April and last for several months.
continue reading → -
Carlton Street Footbridge Rehabilitation Begins
April 22, 2021. Aetna Bridge Company has started work on the rehabilitation of the Carlton Street Footbridge. This steel truss bridge was designed by Alexis H. French, Brookline’s first Town Engineer, working in collaboration with Frederick Law Olmsted, and was constructed in 1894. When the rehabilitation is completed in 2022, pedestrian access over the MBTA Riverside Line from Brookline’s Monmouth neighborhood to Olmsted’s Overlook in Riverway Park will be restored for the first time in more than 45 years.
continue reading → -
Carlton Street Footbridge Rehabilitation Public Information Meeting – March 24, 2021, 6pm
March 19, 2021. Rehabilitation of the historic Carlton Street Footbridge over the Riverside line will begin soon. Learn more at the MassDOT’s virtual public information meeting on March 24, 6-8 pm.
continue reading → -
Dredging Underway at Netherlands Road in Brookline and near Clemente Field in Back Bay Fens: March 90-Day Look-Ahead
March 19, 2021. Dredging has begun in Riverway Park in the Netherlands Road/Parkway Drive/Brookline Avenue area (Work Area 3) and near Clemente Field in the Back Bay Fens (Work Area 9). And there’s more in the U.S. Army Corps of Engineers’ 90-day look-ahead.
continue reading → -
Dredging to Start at Netherlands Road and Parkway Drive: February 90-Day Look-Ahead
February 9, 2021. The U.S. Army Corps of Engineers has advised that dredging in Riverway Park in the Netherlands Road/Parkway Drive/Brookline Avenue area (Work Area 3) is expected to begin in mid-February.
continue reading → -
Temporary Lane Closures at Netherlands Road and on Riverway (outbound) near Brookline Avenue, Friday, February 12
February 9, 2021. The U.S. Army Corps of Engineers has advised that on Friday, February 12, 2021, between 9 am and 3:30 pm, there will be temporary lane closures of about 45 minutes on at Netherlands Road and the Riverway, and on the Riverway at Brookline Avenue to facilitate movement of excavating equipment.
continue reading → -
Dredging in Back Bay Fens and Riverway Park: November 90-Day Look-Ahead
The U.S. Army Corps of Engineers has advised that dredging in Riverway Park (Work Area 2 between Brookline Avenue and the Riverway) will begin in mid to late November and continue until mid-January.
continue reading → -
Temporary Lane Closure on Riverway (outbound) near Brookline Avenue, Monday, December 7
December 3, 2020. The U.S. Army Corps of Engineers has advised that on Monday, December 7, between 9 am and 3:30 pm, there will be a temporary lane closure of about 45 minutes on the Riverway to facilitate delivery of equipment and materials for dredging in Work Area 2.
continue reading → -
Temporary Lane Closure on Riverway (outbound) near Brookline Avenue, Monday, November 30
The U.S. Army Corps of Engineers has advised that on Monday, November 30, between 9 am and 3:30 pm, there will be a temporary lane closure of about 45 minutes on the Riverway to facilitate delivery of equipment and materials for dredging in Work Area 2.
continue reading →