

ABOUT
THE MMOC
Meetings
Volunteers
Resources
MMOC Members
Committees
MUDDY
RIVER RESTORATION PROJECT
Project Documents
Project Updates
Water Quality
Landscape
Flood Control
Best Management Practices
Habitat Enhancement
Maps
Project Updates
Since 2002, certificates under the Massachusetts Environmental Policy Act (MEPA) have been issued by the Secretary of Environmental Affairs requiring Brookline to demonstrate an “enforceable commitment” to restore the Carlton Street Footbridge.
In July, a majority of the Brookline Board
of Selectmen signed a Memorandum of Understanding (MOU) specifying the responsibilities
of the Commonwealth, City of Boston, and Town of Brookline with regard to
the Muddy River Restoration Project. The MOU contains the following statement:
“The Town has authorized $90,000 to date for restoration of the Carlton
Street Footbridge and has committed to the schedule in Attachment A. The SFEIR
requires that the Town demonstrate enforceable commitments with respect to
the Carlton Street Footbridge. If the Town does not demonstrate enforceable
commitments by December 31, 2009, the Commonwealth may terminate this MOU or
may limit its participation or funding under the MOU.
In November, Brookline Town Meeting voted 194-24 for Warrant Article 5 to appropriate $1.4 million for Footbridge restoration. This would include the cost of ramps for accessibility, although the requirement for accessibility must be decided based on consultation with the Mass. Historical Commission and Mass. Architectural Access Board. A Transportation Enhancement Program (TEP) grant could reduce this cost by up to 90%. Town officials are optimistic that this grant would be awarded.
Article 5 provided for 2 schedules. If a TEP grant of at least 60% is awarded, the Town has submitted a schedule with the MOU (referred to above as “Attachment A”) for completion by March 2013. If there is no TEP grant, the Town must execute a contract for restoration within 90 days after a contract is executed by the Army Corps of Engineers for dredging Riverway, Leverett Pond and Willow Pond, and substantially complete restoration on or before the dredging of Riverway, Leverett Pond and Willow Pond is complete.
Over the next several weeks, a Project Participation Agreement (PPA) must be executed between Boston, Brookline, the Commonwealth, and the Army Corps of Engineers. The signing of the PPA is likely in spring, 2010, and construction at the Landmark Center is likely to begin later in 2010.
Recent Improvements and Oversight
Shedding light at Landmark Center: Site Visit
The
parkland in front of the Landmark Center will be “daylighted” (excavated
to open up the original waterway). The jughandle on the south side of Brookline
Ave. is to be removed. The traffic pattern of The Riverway will be changed
to allow a left turn on to Park Drive.
Cleanups Along the Muddy River
![]() |
![]() |
![]() |
|---|
Accessibility at the Longwood MBTA station
Lack
of access for the disabled from the Longwood area of Brookline has prevented
many from enjoying Riverway Park. As part of their improvements for accessibility
at the station, the MBTA has built a ramp from the
Longwood MBTA station across the flood control berm to Riverway Park.



Volunteer Workdays
The
High Street Hill Association in
Brookline has a long history of supporting
restoration efforts in Olmsted Park. A number of “workdays” were
held in 2007 to clean, rake, weed, mulch, and replant the Babbling Brook
and Allerton Overlook areas. Click here for a video of a recent workday. Brookline Parks and Open
Space Division staff supplied guidance, expertise, and equipment.
To sign up for next year, email
us.